Ahmedabad, November 16, 2026 (Yes Punjab News)
Adani Green Energy Limited (AGEL) on Monday said no component of its Tarali pumped storage project (PSP) in Maharashtra falls within a notified Protected Area and that the project does not involve any forest land.
In a statement, an AGEL spokesperson said the company had obtained the necessary permissions and no-objection certificates relating to land use and statutory requirements from the competent authorities.
The spokesperson said the project received Environmental Clearance (EC) on February 11, 2025, followed by Consent to Establish (CTE) from the Maharashtra Pollution Control Board on April 7, 2025. Construction activities began only after the requisite approvals were obtained, the company said.
AGEL added that the wildlife clearance process had also been initiated as part of the Environmental Clearance compliance requirements. The proposal for survey and investigation activities was submitted in January 2025 and subsequently recommended by the State Board for Wildlife. The project proposal has since been submitted to the National Board for Wildlife and is currently under consideration.
The company said the project was being developed in compliance with applicable statutory requirements and directions issued by the competent authorities.
Last week, AGEL had rejected allegations that it reduced the estimated cost of the Tarali project to dilute statutory obligations, describing the claims as misleading.
The company said the online proposal submitted through the forest and wildlife portal related only to site investigation activities. It added that the State Board for Wildlife had considered the total project cost at Rs 5,675 crore.
According to the spokesperson, site investigation costs account for around one per cent of the overall project cost. The company had therefore clarified that the Rs 56.75 crore figure mentioned in the online proposal represented only survey and site investigation expenses.