30.1 C
Delhi
Wednesday, March 27, 2024
spot_img
spot_img

PSPCL waives off charges for shifting of Electrical Lines in Punjab on Capt Amarinder’s orders

Chandigarh, September 4, 2019 (Yes Punjab News)
On the directives of Chief Minister Captain Amarinder Singh, the Punjab State Power Corporation Limited (PSPCL) has exempted domestic and commercial consumers from the material and storage cost, as well as supervision charges, for shifting of 11 KV HT/LT Lines passing over/along their buildings and not having sufficient electrical clearance.

The Chief Minister ordered the PSPCL to issue necessary guidelines in this regard to mitigate the hardships faced by consumers. The move would go a long way in ensuring the safety and security of residents from high tension wires.

The Chief Minister also appealed to the residents to come forward to make optimum use of the benefits offered by the Powercom.

A spokesperson of the Chief Minister’s Office said that the consumers had been bearing 4% of the cost of additional material on account of incidental expenditure, which has now been waived off. The storage charges @ 1.5% on the cost of additional material levied earlier has also been waived off. The transportation and labour charges would also be exempted now in case the same is arranged by the consumer.

The contingencies charges @ 1% on cost of additional material has also been done away with, in a major relief to the consumers. Also, supervision charges which were earlier charged @ 15% on labour charges have been done away with. However, supervision of construction work would be undertaken by PSPCL.

In addition to this, the Audit & Accounts and T & P charges, which were both earlier being levied @1.5% on total cost of estimate, have also been totally abolished.

Referring to additional benefits offered by the Powercom, the spokesman further said the charges would only be recovered from the applicant for the size of the original conductor/cable etc. in case there is an augmentation of conductor/cable etc. Likewise, in case augmentation of transformer is required, the cost of same shall be borne by by the PSPCL.

System improvement work, if any would also be carried out by PSPCL on its own, if required. Apart from these, the payment of fees of Chief Electrical Inspector, if any, for inspection of line, transformer etc. would also be borne by PSPCL.

TOP STORIES

PUNJAB NEWS

TRANSFERS & POSTINGS

Stay Connected

223,537FansLike
113,236FollowersFollow

ENTERTAINMENT

NRI - OCI

GADGETS & TECH

SIKHS

NATIONAL

WORLD

OPINION